Friday, June 25, 2010

Summary of Gowrie's field visit 19.06.2010



Gowrie's team visited the site and was pleased to note that the main rafters for supporting the roof of the building have been fixed. Work is ongoing fixing the cross beams. Interior plastering work is continuing. The blackboards have been fixed.

Further, the base for the 4 new toilets has been built. The septic tank was being dug. Once the new toilets are completed, the renovation of the old toilets will start. All toilet work will be finished before the water supply work will commence.

Ther numbers of workers on the site have been increased. Most are from Katpakapuram Village.