Thursday, June 17, 2010

Gowrie Field Visit Report - 09.06.2010











This time we went to the site in the late afternoon, unlike in the past which has been during the day. This was also an unannouced visit in order to maintain the element of surprise. All Ganam Builders workers and Sam were there.

Work is progressing rapidly on the building. The steel frames for the roof have been mounted. The plastering of all exterior walls and 1 interior room have been completed.

The foundation has been dug for the new toilets

Almost all the workers on the site were from the Katpakapuram village.
I understand from the Engineer that the work on the school building should be completed in 2 weeks time. We will also do a workplan and a financial plan for the other community based work.

No comments: