Tuesday, June 8, 2010

Summary of Gowrie's field visit 29.05.2010



The MT team visited the site well before the planned time in order to add an element of surprise to the visit. We were extremely please to find that Ganam Builders team were in working steadily, with Mr Chandrapalan the supervisor present at the site. We were pleased to note that a remarkable amount of progress has been made in the structure. We were informed that the steel truss which supports the roof has been made and will be mounted on Monday. There were 4 workers from the Katpakapuram village in that days construction team. If work continues at this pace, and good weather holds, it is estimated that all work on the school building can be completed by mid June.

On the toilet and water supply works, we have received estimates from the contractor from the Katpakapuram village contractor and Ganam Builders and we should decide who to give the job in the near future.

Next Field Visit is planned for 5th June