Wednesday, July 21, 2010

Maddam Trust Field Visit (9). 03.07.2010



Work on the new building is almost completed. Only the floor and the 2nd coat of painting interior and exterior remains to be done. It is salmon pinkish colour (unfortunately not pink as pushed by C&C).
New toilet work almost complete, only need the doors to be fitted. Renovation of old toilet completed. The 2 basins have to be plastered as they are leaking.
Ganam Builders will send an estimate for community based work - repairs to old school building and water supply work. Fence and open air stage has been requested by the school principal if there was sufficient available funds. Luca/C&C please advice.
The playground can be done as community voluntary work.
Next Maddam Trust visit will be in 2 weeks