Summary of Gowrie’s field visit report, 6th of May 2010.


Contractor had delivered the first load of building materials even before the Agreement was signed. The type of on site monitoring were agreed upon and it was agreed to arrange for water supply for workers.

School teachers and acting principal were very happy with planned work.
Detailed discussions were held on the planned sanitary projects. It was agreed that there will be an extension to the existing toilet bank to have a total of 6 toilets for the students and 2 toilets for the teachers. Exisiting sewerage drainage system would be checked to ensure that it is working properly. Meeting with the Zonal Educational Direcotr who clarified that only ICTAD registered builders would have been allowed to construct the works and that we had made a good choice of contractor.

There was a discussion on the proposed colour, Engineer informed that only light colour weathershield paint will be approved. Therefore, the purple requested by C&C was not possible. As only whitewashing is included in the estimate, the paint will be an extra cost. There is a light plum colout which is quite cooling ..will send CC the colour chart. Next field visit planned for Saturday 15th May 2010.

No comments:

Post a Comment